Analyst
Faizan Arif
faizan.sufi@pacra.com
+92-42-35869504
www.pacra.com
Applicable Criteria
Related Research
PACRA Assigns Initial Rating to Engro PowerGen Thar (Private) Limited | Privately Placed Sukuk of PKR 3,000mln
Rating Type | Debt Instrument | |
Current (29-Aug-19 ) |
||
Action | Initial | |
Long Term | A | |
Short Term | - | |
Outlook | Stable | |
Rating Watch | - |
Engro Powergen Limited (EPL) along with China Machinery & Engineering Corporation (CMEC) has set up first Thar coal based (2 x 330 MW) power plant (Complex) - Engro Powergen Thar (Pvt.) Limited (EPTL). The company has successfully tested and synchronized its first unit in March-19 and the second unit in April-19 whereby power plant has successfully been connected to and provided electricity to the grid. However, various reliability and performance related tests have been undertaken. Engro Powergen Thar (Pvt.) Ltd achieved COD on 10th July, 2019. The primary fuel is Thar Coal; however, the plant can accommodate imported coal. A 30-year coal supply agreement is signed with Sindh Engro Coal Mining Company (SECMC), which is constructing a coal mine in Thar Block-II. The mine’s contracted COD was Oct-19, which is achieved well before in July-19. The financial strength and experience in the energy chain of the sponsoring companies – EEL and CMEC – is positive to the ratings. The onshore EPC contract is with CERIECO and offshore EPC contract is with CMEC. Offtake agreement is with NTDC, which will, upon plant’s availability as per contract, provide capacity payments even if no dispatch is required by them. The Government of Pakistan has given payment guarantee against dues from NTDC under the Implementation Agreement.
The management’s ability to effectively manage EPC risks provides comfort. Moreover, the timely completion of the affiliated infrastructure projects needed to make the plant operational and the viability of Thar Coal is critical. External factors such as any adverse changes in the regulatory framework, consistency in related policies and performance of the operational benchmarks going forward remain critical for the ratings.
About
the Entity
EPTL, incorporated in September 2014, is set up a 2 x 330 MW Coal-based Power Plant under the 2015 Power Policy. EPTL's majority ordinary shares are owned by Engro Energy Limited (EEL) (50.1%) and China Machinery Engineering Corporation (CMEC) (35%), while the remaining stake is owned by Habib Bank Limited (HBL) (9.5%) and Liberty Mills Limited (LML) (5.4%). Engro Energy Limited (EEL) is 100% owned subsidiary of Engro Corporation.
About
the Instrument
The Company secured PKR 3,000mln through the issuance of rated, secured, and privately placed Sukuk. The proceeds of the Sukuk will be utilized for financing the working capital requirement of EPTL. The tenor of the instrument will be five (5) years starting from the issuance of Sukuk, carrying a mark-up rate of 3 months KIBOR plus 1.10 %. The Sukuk will be having a grace period of around two years from the expiry of availability period or complete drawdown, whichever is earlier. The principal will be paid in quarterly installments. 25% of the issue will be redeemed at the end of third (3rd) year, 25% of the issue will be redeemed at the end of fourth (4th) year, while 50% of the issue will be redeemed at the end of fifth (5th) year. PP Sukuk is secured by way of First Charge over Project Assets with a margin of 20%. The book value of the asset was estimated at USD 1.1bln based on erstwhile Rupee Dollar parity.